A project manager is leading a team that is new to agile. During the kickoff meeting, one team member asks how risks will be managed using agile approaches.

How should the project manager respond?

Answer options

Correct answer: A

Explanation

The correct answer is A, as agile emphasizes collaboration and continuous risk management throughout each iteration rather than relying solely on the project manager. Option B is incorrect because it suggests a more traditional approach where only the project manager handles risks. Option C incorrectly states that risks are managed only during retrospective sessions, which is not frequent enough for effective risk management in agile. Option D misrepresents risk management by implying it occurs only at the kickoff, rather than being an ongoing team responsibility.