Project Management Professional (PMP) — Question 699

A project in the execution phase is part of a large transformation program. The project manager for this project reports to a program manager and also heads the steering committee for this project. A steering committee meeting will be held in the following 2 weeks, during which the approach to measure the schedule performance of the project thus far will be presented.

What should the project manager do in preparation for this meeting?

Answer options

Correct answer: C

Explanation

The correct answer is C because it accurately reflects the use of the schedule performance index (SPI) and other metrics necessary for evaluating the project's progress. Options A and B focus on metrics that are not specifically related to schedule performance, while option D incorrectly suggests that agile methodologies do not utilize performance metrics, which is not true.