A project sponsor asked the product owner to deliver the functionality that provides the highest return on investment (ROI) as soon as possible. Which artifact should the project lead use to track benefits?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Product backlog, as it contains the prioritized list of features and enhancements that can provide the highest ROI. The Requirements backlog is not typically used to track benefits, while the Project charter and Project scope define the project’s objectives and boundaries but do not focus on benefit tracking.