Project Management Professional (PMP) — Question 681
A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late.
What should the project manager do?
Answer options
- A. Engage functional managers to secure roles for team members.
- B. Hold motivation sessions to keep team member morale high.
- C. Ask for replacement project team members.
- D. Penalize team members who arrive to work late.
Correct answer: B
Explanation
The correct answer is B, as holding motivation sessions can help re-energize the team and boost morale during the final phases of the project. Options A and C do not directly address the issue of team focus and morale, while D would likely create a negative environment and further decrease motivation.