Project Management Professional (PMP) — Question 657

A project manager is assigned to lead an enterprise transformation to address change and value delivery at the organizational level. The project manager is working with the team to deliver incremental changes.

What should the project manager do to ensure the success of this endeavor at both the team and organizational levels?

Answer options

Correct answer: B

Explanation

The correct answer, B, is essential because continuously analyzing the impact of changes and associated risks allows for proactive adjustments and informed decision-making, which are crucial for successful incremental delivery. Option A, while important, focuses on buy-in rather than ongoing assessment; C emphasizes governance but lacks the immediate focus on delivery impacts; D is about early collaboration but does not address the continuous evaluation needed for success.