Project Management Professional (PMP) — Question 643

A project manager is working on a hybrid project that has been in progress for the last nine months. Some project stakeholders are becoming frustrated because they do not see the value added by the project.

What should the project manager do to demonstrate the project value?

Answer options

Correct answer: A

Explanation

The correct answer is A because inviting stakeholders to a sprint review allows them to see the tangible progress and value being delivered. Option B, while informative, does not actively engage stakeholders as effectively as a meeting. Option C focuses on challenges rather than demonstrating value, and option D does not address the stakeholders' concerns about the project's benefits.