Project Management Professional (PMP) — Question 641

A project manager is assigned to a parachute development project. Two of the key project resources have a disagreement regarding a requirement.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because referring to the ground rules established at the project's start provides a structured approach to conflict resolution, ensuring that all team members adhere to agreed-upon protocols. Options B and C may lead to unresolved issues or reliance on external opinions, while D relies solely on the project manager's subjective experience, which may not be applicable to the current conflict.