Project Management Professional (PMP) — Question 630

A project manager is managing an iterative project that delivers value incrementally. Over time, the stakeholders have challenged that the team is delivering less value now than they did at the beginning of the project. The project is still predicted to be completed as planned.

How should the project manager respond to the stakeholders?

Answer options

Correct answer: D

Explanation

The correct answer is D because it involves actively investigating the reasons behind the decreased value delivery and taking corrective actions, which shows responsiveness to stakeholder concerns. Options A and C do not address the stakeholders' concerns about perceived value, while option B fails to focus on solutions and does not provide a clear response to the stakeholders' challenge.