Project Management Professional (PMP) — Question 62

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.
What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because the risk response plan outlines actions to take when unexpected events, like losing a key team member, occur. The other options do not directly address the immediate need to manage the impact of this loss on the project timeline.