Project Management Professional (PMP) — Question 61

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.
Which project document should the project manager review in order to determine the reason for this issue?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Stakeholder engagement assessment matrix, which outlines how effectively stakeholders are engaged and informs about their level of involvement. The other options, while relevant to project management, do not specifically address the engagement and communication aspects with stakeholders that are crucial in this context.