Project Management Professional (PMP) — Question 601

A project manager is leading a project when a major crisis suddenly causes an economic downturn, which may threaten the project outcome. What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because documenting new risks is crucial for effective risk management and helps ensure that the project can adapt to the changing circumstances. Options A and C do not address the immediate need for risk assessment, while option B prematurely suggests terminating the project without exploring mitigation strategies.