Project Management Professional (PMP) — Question 6

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?

Answer options

Correct answer: C

Explanation

The project manager selected a hybrid approach because it effectively addresses both the requirement uncertainties and the fixed delivery date. While option A suggests immediate activity initiation, it does not emphasize managing uncertainties, which is critical. Options B and D overlook the balance between requirements and deadlines, making C the most suitable choice.