Project Management Professional (PMP) — Question 58
A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.
What should the project manager do?
Answer options
- A. Create a new standard performance measure based on project requirements
- B. Develop different approaches based on team members' motivation and ability
- C. Develop a standard approach to provide feedback to all team members
- D. Provide intensive oversight to the team members who performed poorly
Correct answer: B
Explanation
The correct answer, B, is effective because it tailors approaches to the individual needs of team members, addressing their specific motivations and abilities. Options A and C provide one-size-fits-all solutions that may not suit everyone, while option D could lead to micromanagement and does not address the root causes of poor performance.