Project Management Professional (PMP) — Question 574
A project manager is in rapid development mode on a joint application development module. The company wants delivery to occur in two weeks. The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog.
What should the project manager do?
Answer options
- A. Push the team to deliver more so that the modules are developed and rolled out according to management's request
- B. Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined
- C. Have the team work toward the tighter deadline so that integration will be easier
- D. Speak to the team and slow the current pace to ensure the team is in alignment with the release date
Correct answer: B
Explanation
The correct answer is B because engaging stakeholders to address the bottleneck can lead to a more efficient process and potential solutions for the delay. Option A is inappropriate as pushing the team may lead to burnout and quality issues. Option C doesn't address the existing backlog and could exacerbate integration problems. Option D suggests slowing down, which would not help in meeting the tight deadlines.