Project Management Professional (PMP) — Question 574

A project manager is in rapid development mode on a joint application development module. The company wants delivery to occur in two weeks. The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because engaging stakeholders to address the bottleneck can lead to a more efficient process and potential solutions for the delay. Option A is inappropriate as pushing the team may lead to burnout and quality issues. Option C doesn't address the existing backlog and could exacerbate integration problems. Option D suggests slowing down, which would not help in meeting the tight deadlines.