A project just kicked off and management's expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers.
What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because identifying the minimum functionality required for the product ensures that the marketing team can effectively present a viable prototype. Options A and B, while helpful in managing the project, do not directly address the immediate need for a functional prototype. Option C suggests prioritization, but without a clear understanding of the minimum requirements, it may not yield the necessary deliverable.