Project Management Professional (PMP) — Question 567

A new project manager is planning an information security project for a company that resides in different countries.
What is the first step the project manager should take to gather customer requirements?

Answer options

Correct answer: A

Explanation

The correct answer is A because conducting a stakeholder analysis is essential to understand how different regional policies impact customer requirements. Options B and D are not effective as they either delegate the analysis process or limit stakeholder engagement to a single location, which may overlook diverse regional needs. Option C, while beneficial, is not the initial step needed to gather comprehensive requirements.