Project Management Professional (PMP) — Question 567
A new project manager is planning an information security project for a company that resides in different countries.
What is the first step the project manager should take to gather customer requirements?
Answer options
- A. Conduct a stakeholder analysis to identify how regional policies may influence needs
- B. Request relevant stakeholders to conduct an analysis and reach consensus independently
- C. Conduct a project scope review workshop with relevant stakeholders
- D. Conduct project planning meetings in one location with relevant stakeholders
Correct answer: A
Explanation
The correct answer is A because conducting a stakeholder analysis is essential to understand how different regional policies impact customer requirements. Options B and D are not effective as they either delegate the analysis process or limit stakeholder engagement to a single location, which may overlook diverse regional needs. Option C, while beneficial, is not the initial step needed to gather comprehensive requirements.