Project Management Professional (PMP) — Question 566

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.
What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer, C, emphasizes the importance of assessing the schedule impact and determining the best course of action to maintain project momentum. Option A, while helpful for communication, does not directly address the deficiencies. Option B could lead to delays, and option D may result in additional complications and costs, making C the most prudent choice.