Project Management Professional (PMP) — Question 558

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because assessing the impact and submitting a change request is the proper procedure for managing scope changes, ensuring that all stakeholders are informed and that the project's integrity is maintained. Option A is incorrect as simply increasing the budget and schedule without a formal change request is not appropriate. Option C overlooks the process for handling scope changes, and option D, while proposing a separate project, does not directly address the sponsor's request within the current project's framework.