Project Management Professional (PMP) — Question 556

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because it addresses the client's concerns directly by involving all parties to establish a clear path to closure while incorporating lessons learned. Option A is not ideal as legal advice may not resolve the immediate project closure issue. Option C ignores the client's valid concerns, and option D, while beneficial for future projects, does not address the current need for closure.