Project Management Professional (PMP) — Question 527

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts.
What should the project manager do in this situation?

Answer options

Correct answer: A

Explanation

The correct answer is A because understanding the stakeholder's concerns and providing regular feedback helps to address issues without escalating tensions or causing further disruptions. Option B may not effectively resolve the concerns, while C does not address the root of the problem. D is too drastic at this stage and may not be necessary if the stakeholder's concerns are properly addressed.