A project manager is implementing a new software system. Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes.
What should the project manager have done at the start of the project to prevent this resistance'?

Answer options

Correct answer: D

Explanation

The correct answer is D, as involving stakeholders from all levels helps to foster understanding and acceptance of the change, reducing resistance. Options A, B, and C, while beneficial, do not directly address the need for comprehensive stakeholder involvement, which is crucial for successful change management.