A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because directly engaging with the team member allows the project manager to understand the root cause of the performance issue. Options B and C may be premature, as they involve external parties without first addressing the individual’s perspective. Option D does not address the underlying issue and could undermine the team member's confidence.