Project Management Professional (PMP) — Question 500

A project manager notices a conflict in the team on both technical and interpersonal levels during the execution phase of a project.
What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because holding a team meeting allows for direct communication, helping to resolve misunderstandings and foster collaboration. Option B is not effective as it only addresses conflicts on a monthly basis rather than immediately. Option C is too late to address ongoing issues, and option D may be unnecessary when internal resolution is possible.