Project Management Professional (PMP) — Question 499
A company plans to initiate a project involving a new technology. Approval for the project is required.
What should the project manager do?
Answer options
- A. Review the cost and schedule baselines for execution.
- B. Define change management for the new technology.
- C. Identify the risks in implementing the new technology.
- D. Analyze the cost and identify the project benefits.
Correct answer: D
Explanation
The correct answer is D because analyzing costs and identifying project benefits are crucial steps for obtaining project approval. Options A, B, and C focus on execution and risk management, which are important but come after securing approval for the project.