Project Management Professional (PMP) — Question 487
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project.
What should the project manager do in this situation?
Answer options
- A. Delegate other team members to complete this team member's tasks.
- B. Mentor the team member and provide the necessary training.
- C. Request the team member to move to another team.
- D. Include the team member in an improvement program through a human resources (HR) request.
Correct answer: B
Explanation
The correct answer is B, as mentoring and providing training will equip the team member with the necessary skills to succeed. Option A is not ideal because it does not support the team member's development, while C suggests removing the team member instead of helping them grow. Option D, involving HR, may not directly address the immediate need for skill development.