Project Management Professional (PMP) — Question 484

A project manager received a request to add features and functions to the project after the scope had already been established.
What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D, as the change management process is specifically designed to handle alterations to the project scope, ensuring that any new requests are properly evaluated and documented. Options A, B, and C focus on different processes that do not directly address the need for managing changes once scope has been established.