A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach.
What should the project manager do to ensure full compliance of quality requirements during the execution phase?
Answer options
- A. Analyze the quality requirements.
- B. Plan quality management
- C. Continually survey the quality of the deliverable
- D. Set up quality policies and procedures
Correct answer: C
Explanation
The correct answer is C because continually surveying the quality of the deliverable ensures that the project remains aligned with the established quality standards throughout execution. Options A and B are more focused on initial assessment and planning rather than active monitoring, while D involves setting up frameworks that do not guarantee ongoing compliance.