Project Management Professional (PMP) — Question 459

An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allow for more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, but also wants to accommodate new information and changes as the project progresses.
Which project management approach should the project manager select for this project?

Answer options

Correct answer: A

Explanation

The Hybrid approach is suitable because it combines structured planning for regulated phases with flexibility for others, allowing the project to adapt as new information arises. Incremental and Agile methods focus more on iterative processes without the necessary upfront planning required here, while the Phased approach lacks the adaptability needed for the more flexible phases.