Project Management Professional (PMP) — Question 458

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches.
What does the project manager need to do first in order to have good project performance?

Answer options

Correct answer: C

Explanation

The correct answer is C because assessing the required training for each team member allows the project manager to identify specific knowledge gaps and tailor training accordingly. Options A and D suggest solutions without first understanding the individual needs, while B involves changing team composition, which may not be necessary if training can address the skill gaps.