A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis. The team member responds that they do not have the knowledge to perform such an analysis.
What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because coaching, mentoring, and training empower team members to build their skills and take ownership of their tasks, fostering a collaborative environment. Options B and D involve escalation or reassignment, which may not address the knowledge gap directly. Option C undermines the development of the team member by doing the work for them rather than helping them learn.