Project Management Professional (PMP) — Question 431

A company is conducting a digital transformation project that has a hard deadline. The marketing team wants to combine this implementation with a new product, and the newly assigned project manager is not aware of all the dependencies.
Using a hybrid approach, what should the project manager do to ensure the dependencies are taken into consideration?

Answer options

Correct answer: D

Explanation

The correct answer is D because facilitating a Scrum of Scrums promotes regular communication and awareness of dependencies across teams, which is essential in a hybrid approach. Option A, while informative, does not directly address dependency management. Option B focuses on alignment but may overlook interdependencies. Option C could complicate the project structure and hinder collaboration rather than enhance it.