Project Management Professional (PMP) — Question 411
A company is initiating a project to enhance one of its existing products. All of its products are developed internally.
What should the project manager do?
Answer options
- A. Ensure the stakeholder engagement plan is accurate and properly documented
- B. Review the lessons learned from the previous project
- C. Identify the risk of implementing the new solution and evaluate the impact on the project
- D. Create a lessons learned document for the initiation phase
Correct answer: B
Explanation
The correct answer is B because reviewing lessons learned from previous projects helps the project manager identify what worked well and what didn't, providing valuable insights for the current project. Options A, C, and D are important tasks but do not prioritize the lessons learned, which can significantly influence the success of the new enhancement.