Project Management Professional (PMP) — Question 405

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track.
What will the project manager need to focus on as a result of this decision?

Answer options

Correct answer: C

Explanation

Choosing to skip testing can lead to increased technical debt as unresolved issues may accumulate, making future development more complex and costly. The other options may also be consequences, but they do not directly relate to the immediate effects of bypassing testing in the project.