Project Management Professional (PMP) — Question 403
Close to the end of a project, a customer claims that some deliverables have not been met and starts initiating change requests.
What should the project manager do next?
Answer options
- A. Refer to the requirements traceability matrix.
- B. Escalate the change request to the project sponsor.
- C. Revise the project scope baseline.
- D. Review the approved project charter.
Correct answer: A
Explanation
The correct answer is A because the requirements traceability matrix helps to verify whether all project deliverables have been completed according to the initial specifications. Options B, C, and D do not address the immediate need to confirm whether the deliverables were indeed met based on the documented requirements.