A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
What should the project manager do?
Answer options
- A. Review the communications management plan to identify new stakeholders.
- B. Define a risk management plan for the new approach, as needed.
- C. Define a project management plan for the new approach, as needed.
- D. Review the benefits realization plan to include the cost of the change.
Correct answer: D
Explanation
The correct answer is D because reviewing the benefits realization plan ensures that the costs associated with switching approaches are accounted for, which is crucial for the project's financial planning. Options A, B, and C do not directly address the immediate concern of managing the financial implications of changing the project management approach.