A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.
What should the project manager do next?
Answer options
- A. Take on some of the necessary work to minimize the impact.
- B. Invite the stakeholders to discuss a mitigation plan.
- C. Detail the reason for the project delay in the status report.
- D. Register an issue and escalate it to the project sponsor.
Correct answer: B
Explanation
The correct answer is B because involving stakeholders in a discussion about a mitigation plan allows for collaborative solutions and resource allocation to address the gap left by the departing team member. Option A, while proactive, does not engage stakeholders or address the broader implications. Option C focuses on reporting rather than resolving the issue, and option D, although valid, does not prioritize immediate stakeholder engagement to find a solution.