Project Management Professional (PMP) — Question 366

A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?

Answer options

Correct answer: B

Explanation

The correct answer is B, as evaluating the quality checklist ensures that the product meets the necessary standards before delivery. Options A and C focus on budget and exit criteria, which do not directly address quality assurance. Option D, while important, pertains to integration testing rather than overall product quality compliance.