Project Management Professional (PMP) — Question 36
A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project manager use to manage these risks using an agile approach?
Answer options
- A. Develop an agile risk matrix to track, assess, and evaluate the uncertainty of the project.
- B. Implement a scrum risk retrospective to analyze the risks at the end of the project.
- C. Assign an agile risk manager to better understand and track the project risks.
- D. Evaluate the risks constantly and reprioritize work as the project progresses.
Correct answer: D
Explanation
The correct answer, D, emphasizes the agile principle of adaptability by constantly evaluating risks and adjusting priorities, which is essential in a high-uncertainty environment. Options A and C suggest tools or roles that may help but do not inherently embody the iterative nature of agile risk management. Option B focuses on analyzing risks only at the end of the project, which may be too late to effectively mitigate them.