Project Management Professional (PMP) — Question 36

A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project manager use to manage these risks using an agile approach?

Answer options

Correct answer: D

Explanation

The correct answer, D, emphasizes the agile principle of adaptability by constantly evaluating risks and adjusting priorities, which is essential in a high-uncertainty environment. Options A and C suggest tools or roles that may help but do not inherently embody the iterative nature of agile risk management. Option B focuses on analyzing risks only at the end of the project, which may be too late to effectively mitigate them.