Project Management Professional (PMP) — Question 35
A project schedule risk has turned into an issue. The project manager foresees delays in project execution.
What should the project manager do to resolve the issue?
Answer options
- A. Escalate the issue to senior leadership for resolution
- B. Work with relevant stakeholders to determine possible solutions
- C. Update the schedule baseline to the new project time line
- D. Update the risk management plan and send it to the project team
Correct answer: B
Explanation
The correct answer is B, as it involves collaborating with stakeholders to identify solutions, which is essential for effective problem resolution. Option A is not ideal because escalating may not provide immediate solutions. Option C is inappropriate since updating the schedule without addressing the root cause won't resolve the delays. Option D focuses on documentation rather than actively solving the issue.