Project Management Professional (PMP) — Question 357

The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.
What should the project manager do first?

Answer options

Correct answer: D

Explanation

The project manager should first meet with the operations manager to gain a better understanding of the concerns about the change and provide context for the decision. This dialogue is crucial for addressing the operational impact before taking further actions. Options A, B, and C are reactive and do not prioritize understanding the immediate concerns of the operations manager.