A project manager is assigned to a technical research project. The project team has already been assigned, and the main subject matter expert (SME) sends the project manager a list of the technical skills required for the execution of this project.
What should the project manager do next?

Answer options

Correct answer: C

Explanation

The correct answer is C because meeting with the project team allows the project manager to gain insights into their existing skills and identify any training needs. Option A is not appropriate at this stage since confirming skills is less effective than directly assessing them. Option B does not involve the team directly, which is crucial for understanding their capabilities. Option D assumes the team will independently seek training without the project manager's guidance, which is less effective for project alignment.