A project manager is assigned to a technical research project. The project team has already been assigned, and the main subject matter expert (SME) sends the project manager a list of the technical skills required for the execution of this project.
What should the project manager do next?
Answer options
- A. Discuss the list with the project sponsor to confirm that the resources have the required skills.
- B. Ask the functional manager to review the resource pool and recommend the right individuals to join the team.
- C. Meet with the project team to understand their skills and identify potential gaps and training requirements.
- D. Send the list to the project team and ask them to get training on the required skills.
Correct answer: C
Explanation
The correct answer is C because meeting with the project team allows the project manager to gain insights into their existing skills and identify any training needs. Option A is not appropriate at this stage since confirming skills is less effective than directly assessing them. Option B does not involve the team directly, which is crucial for understanding their capabilities. Option D assumes the team will independently seek training without the project manager's guidance, which is less effective for project alignment.