Project Management Professional (PMP) — Question 342

A project manager is leading a project team composed of members with varying levels of knowledge and experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.

What should the project manager do?

Answer options

Correct answer: B

Explanation

Option B is the correct choice because mentoring allows less-experienced members to learn from their knowledgeable peers, fostering skill development and team cohesion. Option A limits learning opportunities, while Option C may not provide sufficient support for skill growth. Option D can disrupt team dynamics and is not a constructive solution for developing the team's capabilities.