Project Management Professional (PMP) — Question 342
A project manager is leading a project team composed of members with varying levels of knowledge and experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.
What should the project manager do?
Answer options
- A. Ask the less-experienced members to perform tasks exactly as they are instructed by the experienced members.
- B. Ask each experienced member to be the mentor to one of the less-experienced members.
- C. Ask the more experienced members to review all of the tasks performed by the less-experienced members.
- D. Ask the resource manager to replace the less-experienced members with more experienced team members.
Correct answer: B
Explanation
Option B is the correct choice because mentoring allows less-experienced members to learn from their knowledgeable peers, fostering skill development and team cohesion. Option A limits learning opportunities, while Option C may not provide sufficient support for skill growth. Option D can disrupt team dynamics and is not a constructive solution for developing the team's capabilities.