Project Management Professional (PMP) — Question 33
A project manager is managing a complex research project with a high level of uncertainty. A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
Answer options
- A. Scrum master reviews and the quality Kanban method.
- B. Daily Scrum and product owner quality assessments.
- C. Paired work and the customer role method.
- D. Time-boxed iterations and standup review meetings.
Correct answer: D
Explanation
The correct answer is D because time-boxed iterations allow for regular assessment of deliverables, while standup review meetings facilitate ongoing feedback and adjustments. Options A, B, and C do not incorporate the effective iterative framework and team collaboration needed for measuring quality in a hybrid approach.