After conducting a performance assessment, the project manager identified that some gaps still exist.
What should the project manager ensure?
Answer options
- A. Awards are given to all team members for playing a role in the project and undertaking the assessment.
- B. Performance improvement programs are organized for all team members who were assessed.
- C. All team members rotate their job schedules immediately to make them versatile.
- D. Assessment results are kept private and not shared among team members.
Correct answer: B
Explanation
The correct answer is B because organizing performance improvement programs directly addresses the identified gaps by providing targeted support for the team. Option A, while promoting morale, does not address the performance issues. Option C focuses on job rotation, which may not be necessary for addressing specific performance deficiencies. Option D hinders transparency and learning, which are crucial for improvement.