Project Management Professional (PMP) — Question 312

A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because the project has already met its closure criteria, and releasing the remaining budget and resources is the appropriate step. Options A and D suggest adding scope, which contradicts the closure phase, while option B focuses on quality checks rather than project closure.