Project Management Professional (PMP) — Question 283
A company is working on a project to develop an integration of their existing systems. There are known issues in production.
What should the project manager do?
Answer options
- A. Identify and remove impediments and mitigate the risks.
- B. Ensure the product owner reviews requirements with the team.
- C. Include acceptance criteria in the definition of done (DoD).
- D. Review the quality control processes and procedures.
Correct answer: A
Explanation
The correct answer is A because addressing impediments and mitigating risks is crucial to ensure that the integration project progresses smoothly, especially when there are known issues. Options B, C, and D, while important for project management, do not directly address the immediate need to resolve existing production problems.