Project Management Professional (PMP) — Question 266

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team.
What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because allowing team members to choose their teams can enhance motivation and collaboration, which aligns with agile principles. Options A and B are incorrect as they disregard team members' preferences, which can lead to disengagement. Option D is also wrong, as it does not consider the input and desires of the current team members.