An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.
What should the project manager do?
Answer options
- A. Add 4 additional weeks to the schedule and request additional resources.
- B. Ask the sponsor to obtain a special work permit to continue work.
- C. Crash the resource management plan to keep the schedule on track.
- D. Review the project management plan to see the impact of the possible delay.
Correct answer: D
Explanation
The correct answer is D because reviewing the project management plan is essential to understand how the delay will affect the project and to determine the next steps. Options A and C propose adjustments that may not be necessary without first analyzing the impact of the delay, while option B may not be feasible or appropriate in this situation.