Project Management Professional (PMP) — Question 256

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.
What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because reviewing the project management plan is essential to understand how the delay will affect the project and to determine the next steps. Options A and C propose adjustments that may not be necessary without first analyzing the impact of the delay, while option B may not be feasible or appropriate in this situation.