Project Management Professional (PMP) — Question 250
A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress (WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.
What should the project manager have done to avoid this situation?
Answer options
- A. Stored project documentation in a shared folder.
- B. Organized monthly meetings with the external stakeholders.
- C. Invited all of the stakeholders to daily standup meetings.
- D. Sent weekly status update reports to all of the stakeholders.
Correct answer: D
Explanation
The correct answer is D because sending weekly status update reports keeps stakeholders informed and reduces the likelihood of them feeling the need to pause the project for updates. Options A and B do not ensure regular communication, while C may not be practical for all stakeholders given the frequency of daily meetings.