Project Management Professional (PMP) — Question 249
A solution designer in an agile team often passes the design information to team members without any documentation. This has resulted in misunderstandings within the team.
What should the agile leader do?
Answer options
- A. Move the solution designer to another team
- B. Review the process that resulted in this situation
- C. Ask the team to document the design
- D. Stop work until the design document is completed
Correct answer: B
Explanation
The correct answer is B, as reviewing the process allows the agile leader to identify and rectify the root cause of the communication breakdown. Options A, C, and D do not address the underlying issue of ineffective communication and may lead to further complications without resolving the initial problem.